A roof replacement looks chaotic from the driveway: a dumpster, a crew on the roof, debris sliding into tarps, and noise from first light. Underneath that noise is a fixed sequence, and knowing the roof replacement process step by step helps you check that nothing was skipped.
This guide walks through re-roof day in order, from the week before to the final walk-around. It draws on the asphalt roofing industry’s installation manual, the FORTIFIED re-roofing standard and Plano’s adopted building code. It has no prices and no promised timelines, because both depend on the roof.
What is the roof replacement process, step by step?
The roof replacement process runs in a fixed order: protect the property, tear the old roofing down to the deck, inspect and repair the decking, install drip edge and underlayment, flash the edges and penetrations, lay the shingles from the eaves up, finish the ridge and vents, then clean up and walk the job with you.
Each step depends on the one before it. Shingles laid over soft decking will not stay flat, and flashing installed after the shingles is a patch rather than a system. The overview below is the order an asphalt shingle re-roof normally follows.
| Step | What happens | What you can check |
|---|---|---|
| 1. Preparation | Tarps, dumpster, access, attic cover | Shrubs and items near walls protected |
| 2. Tear-off | Old shingles and underlayment removed to the deck | No new roof laid over old layers unless agreed |
| 3. Deck inspection | Rotten or damaged boards found and replaced | Photos and a count of replaced sheets |
| 4. Edges and underlayment | Drip edge, underlayment, self-adhering membrane | The underlayment named in your contract |
| 5. Flashing | Valleys, walls, chimneys, vents, skylights | New flashing where the contract says new |
| 6. Shingles | Starter strip, then courses up to the ridge | Straight lines, no exposed nails |
| 7. Ridge and vents | Hip and ridge caps, ventilation | Vents match the plan |
| 8. Clean-up and walk-through | Debris removed, nail sweep, final look | Gutters cleared, yard swept |
What happens before the crew arrives?
Before re-roof day, the contractor should confirm the material order, the start date, the permit position and the plan for weather. You should clear the driveway for the dumpster, move cars and outdoor furniture away from the walls, and take fragile items off walls inside, because tear-off vibrates the whole house.
Plano adopted the 2024 International Residential Code, with local amendments, through Ordinance 2025-6-15. Its amended section R105.3 requires a permit applicant to be registered with the city as a contractor, with an exception for homeowners working on their own residence. Ask your contractor who will apply and when, and confirm with Plano Building Inspections what your job requires.
Be wary of any contractor who asks you to pull the permit yourself. The Federal Trade Commission’s guide to avoiding home improvement scams lists asking you to get the required building permits among the warning signs of a scam.
A short pre-start checklist:
- Written contract with the shingle line, underlayment and flashing scope named.
- Agreement on how decking replacement is counted and charged.
- Start date and the weather plan if rain is forecast.
- Where the dumpster goes and how the driveway is protected.
- Who to call on site if something goes wrong.
How is the old roof torn off?
Tear-off means stripping the old shingles, underlayment and worn flashing down to the wooden deck. The crew protects the house and yard first, works section by section, and sends debris into a dumpster or onto tarps. The goal is a clean, bare deck that can be inspected before anything new goes on.
The Asphalt Roofing Manufacturers Association (ARMA) sets this out in its Residential Asphalt Roofing Manual. Where existing roofing must be removed, it says to strip the materials completely down to the roof deck. It tells crews to protect the existing structure and surrounding grounds, attic contents, plumbing vents and gutters, and to follow OSHA regulations.
The same manual lists tarps among the tools of the job, used to cover shrubs and protect landscaping from falling debris. It also warns against concentrating bundles of new shingles in one spot on the deck; they should be spread out to distribute the load.
Inside the house, expect dust and small debris to fall from the attic. Cover stored items in the attic, or ask whether the crew will do it.
Tear-off is also the loudest part of the job. Hammering and scraping carry through the whole house, so plan around pets that stress easily and anyone working from home. Keep children and pets indoors or away from the walls while debris is coming down, because nails and shingle pieces can land well beyond the tarps. Agree a safe route to the front door before work starts.
Can new shingles go over the old roof instead?
New shingles can sometimes go over one existing layer, but a full tear-off is the more common choice for a replacement. ARMA says the old shingles will probably have to be removed when the deck shows rot, when there are already two layers, when the roof sags, or when the old shingles are too uneven to lie flat.
ARMA’s technical bulletin on reroofing, replacement versus recover defines the two options. A roof recover installs a new covering over the existing one. A roof replacement removes the existing covering, repairs damaged substrate and installs a new covering.
The bulletin adds that most building codes do not allow more than two roof coverings on a building. ARMA’s manual also notes that most manufacturers do not recommend installing over laminated shingles.
If you want to pursue the FORTIFIED Roof designation from the Insurance Institute for Business & Home Safety, its re-roofing checklist requires removing all existing roofing material and replacing any damaged wood.
What happens when the roof deck is exposed?
Once the deck is bare, the crew inspects it for rot, soft spots, delamination and gaps. Damaged boards are cut out and replaced before anything else goes on. This is the one point in the job when hidden damage becomes visible, so it is also the point where the price can change if decking was priced per sheet.
ARMA’s reroofing bulletin says any rotten or damaged boards must be replaced before new shingles are applied. It also says that if the roof structure sags across the ridge or truss lines, the structure should be inspected by a licensed structural engineer. That is not a decision for the roofer alone.
Ask for photos of any decking that is replaced, and a count that matches the invoice. A good contractor offers this without being asked.
Some owners use this stage to upgrade the deck. The FORTIFIED checklist, for example, requires re-nailing the deck with ring-shank nails at a set spacing and sealing the deck seams. These are optional upgrades unless you are seeking that designation.
Exposed decking is also a rain risk. Our guide to rain during a re-roof covers how long underlayment can stay uncovered and what a crew should do when a storm arrives mid-job.
How are underlayment, drip edge and flashing installed?
After the deck is sound, the crew installs metal drip edge along the eaves and rakes, then covers the deck with underlayment. A self-adhering membrane goes in the most leak-prone areas, such as valleys and around chimneys and skylights. Flashing is then fitted wherever the roof meets a wall or is broken by a penetration.
ARMA’s manual says the use of a drip edge is strongly recommended and may be required by local building codes. It lists the critical areas where self-adhering underlayment is commonly used as eaves, rake edges, valleys, around skylights and chimneys, dormers, slope transitions and low-slope areas.
Flashing is where a re-roof is most often cut short. Ask your contractor three questions:
- Will the valley flashing be new?
- Will the wall and chimney flashing be replaced or reused?
- Will the pipe boots on plumbing vents be new?
Reused flashing is not always wrong, but it should be a stated decision in the contract, not a surprise.
How are the new shingles laid?
The crew starts with a starter strip at the eaves, then lays shingle courses upward toward the ridge, offsetting each row so that joints never line up. Each shingle is nailed in the pattern the manufacturer specifies. Hip and ridge caps finish the peaks, and roof vents are installed or replaced to match the ventilation plan.
ARMA’s manual describes strip shingles fastened with four nails positioned above the exposure, and it says to consult the manufacturer’s instructions for details. Nail placement matters because the manufacturer’s warranty usually depends on following those instructions.
From the ground you can look for:
- Straight, even courses when viewed from the street.
- Ridge caps that follow the line of the ridge.
- No nail heads showing on the finished surface.
- Vents and pipe boots sitting flat, with shingles lapped neatly around them.
Do not climb onto the roof to check. Look from the ground or from a window, and ask the contractor for photos of any area you cannot see.
What does clean-up and the final walk-through include?
Clean-up should leave the property as it was before work began. That means removing debris, clearing gutters of granules and nails, running a magnetic sweep over the lawn and driveway, and taking down tarps. The final walk-through is your chance to ask questions, see photos and agree that the job is finished.
ARMA lists a magnetic roller for picking up nails around the job site after the work is completed. Ask for a second sweep if you find nails in the following days.
At the walk-through, ask for:
- Photos of the deck, underlayment and flashing taken during the job.
- The shingle product name and colour, for your records and your HOA.
- The warranty paperwork and any registration steps. Our guide to roof warranty types explains manufacturer and workmanship cover.
- The permit final, where a permit was required.
Hold back the final payment until you are satisfied. The FTC advises never making the final payment until the work is done and you are happy with it.
For the wider planning picture, from timing to taxes, see our guide to planning a re-roof in Plano. When you want a written scope for your own home, Roofing Repair Plano provides roof replacement in Plano and nearby cities.
Frequently asked questions
What are the steps of a roof replacement?
A typical asphalt shingle replacement follows eight steps: protect the property, tear off the old roof to the deck, inspect and repair the decking, install drip edge and underlayment, flash valleys, walls and penetrations, lay the shingles from the eaves up, cap the ridge and fit vents, then clean up and walk the job with the owner.
Do I need to be home during a roof replacement?
You do not have to be home all day, but be reachable. The crew may find damaged decking that needs your approval, and someone should confirm access, pets and parking at the start. Plan to be there for the final walk-through, so you can see photos, collect warranty paperwork and agree the job is finished.
What happens if roofers find rotten wood?
Rotten or damaged decking must be replaced before new shingles go on, according to ARMA’s reroofing guidance. Your contract should say how replacement sheets are counted and charged. Ask for photos and a count. If the structure itself sags, ARMA advises an inspection by a licensed structural engineer before roofing continues.
Can a new roof be installed over old shingles?
Sometimes, over a single flat layer on a sound deck. ARMA says most codes do not allow more than two roof coverings and that the old roof should come off if the deck is rotten, the roof sags or the shingles are too uneven. Most manufacturers do not recommend installing over laminated shingles.
How do I protect my yard during a roof replacement?
Move cars, grills and furniture away from the walls before the crew arrives, and ask the contractor to tarp shrubs and flower beds. ARMA lists tarps for protecting landscaping and a magnetic roller for picking up nails after the job. Walk the yard afterwards and ask for a second sweep if needed.